Lenders line up 80 MW of solar while a USD 2bn grid waits
80 MW of solar in Zimbabwe and Tunisia now has named lenders, 30 MW at Vungu and 50 MW at Tataouine, and neither is at financial close. |
4 claims this week rested on a single social media post and are not counted by AEI. |
4 procurement deadlines fall before 14 Dec. |
Lenders commit to small guaranteed solar first, and the USD 2 billion grid is still an approval
In Zimbabwe, Standard Bank South Africa and Stanbic Bank Zimbabwe were appointed to lead the financing of the 30 MW Vungu solar project, which already holds a 25 year power purchase agreement with ZETDC and a government support agreement. In Tunisia, EBRD and the Clean Technology Fund are reported to have secured EUR 50 million (USD 55.4 million) for the 50 MW Tataouine solar plant with a 10 MW / 20 MWh battery, about EUR 1.0 million per MW. Neither is financial close. AEI does not count financial close until a party to the deal says the financing has closed.
The pattern is the same as last week. Standard Bank and its Stanbic affiliates now front the financing of Vungu, Guruve-Mazowe and Ngonye Falls, and capital is arriving first where an offtaker or a sovereign stands behind the cash flow. Nigeria shows the other end of the market. The Federal Government has approved USD 2 billion for the East-West Super Grid, at least 19,000 MW of additional transmission capacity, about USD 105,000 per MW, with procurement under way and delivery put at 1.5 to 2 years by the power minister. A ministerial approval is not a funded lender group, and the China Exim Bank loan sought in 2025 has not been reported as signed.
For a lender, small ticket deals with a PPA and a guarantee are the bankable end of the pipeline, and the next test is whether credit committees approve them on terms. For a sponsor, a mandate letter and a development bank commitment save time but do not fix price or tenor, so the debt share and the margin are still open. For an investor, 19,000 MW of grid on a USD 2 billion envelope depends on who actually lends, and until then the cash is a policy statement.
The Libyan dinar's 18% fall and the projects it hits
| Libyan dinar, 18% weaker over the year. 7 screened projects in Libya, 1.6 GW. On AEI's standard split, half the tariff tracking the dollar, the unsupported case now breaks 1.0x DSCR in year 5 at the past year's pace, against year 7 on AEI's 10% assumption. The dollar-linked share of the tariff moves the rest of the risk to Libyan Iron and Steel Company (LISCO): 1 of 7 projects could not carry a six-month payment delay without liquidity support; with six months of cover, all of them could. Low confidence: tariff split is AEI's standard assumption. |
Projects that changed stage this week
| Project | Market | Change |
|---|---|---|
| Vungu Solar Project, 30 MW | Zimbabwe | Financing under way, Standard Bank South Africa and Stanbic Bank Zimbabwe appointed (8 Nov) |
| Kamoa-Kakula Solar + BESS Supply, 60 MW | DR Congo | In operation, Ivanhoe reports 60 MW of continuous supply (8 Nov) |
| Nigeria Super Grid, 19 GW | Nigeria | Moved to late development, USD 2 billion approved and procurement under way (10 Nov) |
| Eskom Phase 1 Renewable Energy and BESS Program, 2 GW | South Africa | Tender launched, 5 year panel for up to 6 GW, Phase 1 at least 2 GW of solar and 1 GW / 4 GWh of storage (11 Nov) |
| Tataouine 50 MW Solar PV Plant with BESS, 50 MW | Tunisia | Financing under way, EUR 50 million reported from EBRD and CTF (12 Nov) |
Deadlines to 14 Dec
| Date | Market | What closes |
|---|---|---|
| 16 Nov | South Africa | Submissions for Eskom Green Phase 1 Strategic Partner Programme (up to 6 GW) |
| 26 Nov | Ethiopia | Submissions for PRIME 1 - Debark and Injibara 230 kV Transmission Lines |
| 30 Nov | Morocco | Prequalification for NOOR PV Multisites Programme |
| 7 Dec | Mauritius | Bids for Tamarind Falls Floating Solar and BESS Project |
Claims AEI has not accepted
| "SIFCA, EDF, and Meridiam commission 46 MW Biovéa biomass power plant in Côte d'Ivoire." One social media post, with no statement from a party to the deal. |
| "EBRD provides $63.5 million for Egyptian solar and storage project." One social media post, with no statement from a party to the deal. |
| "Okra Solar secures $7 million debt facility from BII for Nigerian decentralised solar rollout." One social media post, with no statement from a party to the deal. |
| "StarTimes Uganda seeks $33.3 million IFC financing for solar home systems distribution." One social media post, with no statement from a party to the deal. |