Egypt's guarantee takes Dandara to 80% debt
1.77 GW of Egyptian solar moved into construction across two projects, with 700 MWh of storage, both with EBRD in the lender group. |
80% is the share of Dandara Phase 1's cost funded by debt, ten points above the 70% AEI applies to a B-rated country with no payment security. |
One social media post is the only source behind reports that South Africa's 2,000 MW gas tender closed without a winner. |
A sovereign guarantee is worth ten points of gearing in Egypt
Scatec signed loan agreements for Dandara Phase 1 on 28 October and started construction: 569 MW of solar and 100 MWh of storage, USD 217 million of limited recourse debt from EBRD, AfDB and EIB against USD 271 million of capex. The buyer is Egypt Aluminium, under a 25-year US dollar PPA backed by a sovereign guarantee.
For a country rated B by S&P, AEI's finance screen sizes debt at 1.40 times cover on P90 output, over 15 years, at a 450 basis point margin, which caps debt at 70% of cost. Six months of liquidity cover, the structure behind Scaling Solar and GET FiT, lifts the cap to 75%. Dandara's lenders went to about 80%.
Those ten points matter. On a USD 271 million project, moving from 70% to 80% debt is about USD 27 million of equity the sponsors do not have to put in. That is what a sovereign guarantee on a hard currency PPA buys in Egypt today, and why the same lenders keep returning: Nefer Minya, the other Egyptian project to start construction this week, carries up to USD 566 million of debt arranged with EBRD.
For other markets the lesson is direct. Resource and tariff decide whether a project works. Payment security decides how much of it lenders will fund.
Dandara Phase 1 against AEI's terms for a B-rated country
On the Dandara page in AEI, the loan terms still to be agreed for a project of this kind include tariff currency and indexation, storage remuneration and political risk cover, each with the African deals that settled them.
| No payment security | Six months of liquidity cover | Dandara Phase 1 | |
|---|---|---|---|
| Payment security | Professional | Professional | Professional |
| Debt share of cost | Professional | Professional | Professional |
| Debt on USD 271 million of cost | Professional | Professional | Professional |
| Equity the sponsors fund | Professional | Professional | Professional |
Projects that changed stage this week
| Project | Market | Change |
|---|---|---|
| Dandara Phase 1, 569 MW solar and 100 MWh storage | Egypt | Loan agreements signed, construction started (28 Oct) |
| Nefer Minya, 1.2 GWp solar and 600 MWh storage | Egypt | Notice to proceed issued for full construction (27 Oct) |
| Diaz Wind, 44 MW | Namibia | In operation, 32 MW already generating (23 Oct) |
| Mashi 120 MVA substation, Katsina | Nigeria | Ground broken, completion targeted for March 2027 (23 Oct) |
| Kurra hydro rehabilitation, 11.5 MW | Nigeria | Moving to financial close under the UK PACT programme (29 Oct) |
Deadlines to 30 November
| Date | Market | What closes |
|---|---|---|
| 10 Nov | South Africa | Responses to the 2026 Renewable Energy Grid Survey, extended from its original date |
| 12 Nov | Rwanda | Prequalification for the 200 MW Lake Sake floating solar IPP with 800 MWh of storage (EDCL) |
| 19 Nov | Botswana | Expressions of interest for floating solar on Water Utilities Corporation dams |
| 26 Nov | Ethiopia | Bids for the Debark and Injibara 230 kV transmission lines (PRIME 1) |
| 30 Nov | Morocco | Contractor submissions for the 350 MW Noor PV Multisites programme |
Claims AEI has not accepted
| "AfDB backs Dandara with USD 650 million." USD 650 million is the reported size of the whole project. AfDB's commitment is up to USD 66 million: USD 46 million from its own resources and USD 20 million from the Clean Technology Fund. |
| "Dandara reaches financial close." Scatec reports signed loan agreements and the start of construction. AEI will use financial close when a party to the deal does. |
| "South Africa's 2,000 MW gas tender closes without a preferred bidder." One LinkedIn post, with no statement from the Ministry of Electricity and Energy. |
New on the platform
| Open loan terms on every screened project. Each project page lists the terms a lender will still need to agree, with the African deals that settled them. |
| One-page finance notes. Download a project's finance case as a PDF, or post it to LinkedIn as a ready-made image. |
| Debt terms benchmarks from 55 African deals. Compare tenor, margin and cover against what lenders have actually agreed. |
| Utility payment risk by country. Decision packs cover ZESCO, Kenya Power, Eskom, EETC and STEG. |
| 16 technology categories. Filter by solar, wind, storage, hydrogen, bioenergy, clean cooking and more. |