MW reaching operation
7,738
184 projectsMission 300, led by the World Bank and the African Development Bank, aims to connect 300 million Africans to electricity by 2030. This page counts only what AEI can evidence in each compact country since its compact was presented: capacity reaching construction and operation, financial closes, and the payment security lenders need. Partner-reported connections are not counted here.
7,738
184 projects2,300
22 projects28
since the compacts9 of 85
signed PPAs with evidenced security| Market | Compact | MW to operation | MW to construction | Closes | PPAs with security | Verified | Access pace |
|---|---|---|---|---|---|---|---|
| Cohort 1 2025-01-28 | 2,180 | 30 | 1 | 0 of 1 | 2% | No pace test | |
| Cohort 1 2025-01-28 | 1,645 | 190 | 2 | 0 of 11 | 10% | Behind pace | |
| Cohort 1 2025-01-28 | 1,063 | 1,422 | 2 | 2 of 18 | 18% | Definitions differ | |
| Cohort 1 2025-01-28 | 932 | 60 | 0 | 0 of 2 | 7% | Definitions differ | |
| Cohort 2 2025-09-25 | 276 | 0 | 1 | 0 of 4 | 15% | Behind pace | |
| Cohort 2 2025-09-25 | 257 | 100 | 0 | 0 of 0 | 17% | On pace | |
| Cohort 2 2025-09-25 | 211 | 0 | 0 | 0 of 1 | 10% | Definitions differ | |
| Cohort 2 2025-09-25 | 154 | 0 | 1 | 0 of 5 | 13% | Definitions differ | |
| Cohort 2 2025-09-25 | 125 | 0 | 1 | 0 of 1 | 12% | Behind pace | |
| Cohort 1 2025-01-28 | 105 | 50 | 6 | 1 of 6 | 16% | Definitions differ | |
| Cohort 3 2026-06-16 | 100 | 0 | 0 | 0 of 0 | 43% | Behind pace | |
| Cohort 1 2025-01-28 | 89 | 30 | 2 | 0 of 1 | 7% | Definitions differ | |
| Cohort 3 2026-06-16 | 76 | 0 | 1 | 0 of 3 | 31% | Behind pace | |
| Cohort 1 2025-01-28 | 73 | 0 | 2 | 1 of 5 | 13% | Behind pace | |
| Cohort 2 2025-09-25 | 66 | 0 | 0 | 0 of 1 | 15% | Definitions differ | |
| Cohort 2 2025-09-25 | 63 | 0 | 0 | 0 of 2 | 13% | Behind pace | |
| Cohort 1 2025-01-28 | 62 | 0 | 0 | 1 of 1 | 18% | Behind pace | |
| Cohort 3 2026-06-16 | 60 | 0 | 0 | 0 of 1 | 9% | Definitions differ | |
| Cohort 3 2026-06-16 | 44 | 0 | 0 | 0 of 0 | 7% | Behind pace | |
| Cohort 1 2025-01-28 | 42 | 60 | 3 | 2 of 3 | 15% | Behind pace | |
| Cohort 2 2025-09-25 | 40 | 0 | 0 | 0 of 0 | 0% | Definitions differ | |
| Cohort 2 2025-09-25 | 40 | 0 | 0 | 0 of 0 | 17% | Behind pace | |
| Cohort 1 2025-01-28 | 30 | 358 | 0 | 0 of 2 | 9% | Definitions differ | |
| Cohort 2 2026-04-30 | 3 | 0 | 3 | 2 of 4 | 10% | Definitions differ | |
| Cohort 1 2025-01-28 | 2 | 0 | 1 | 0 of 2 | 0% | Behind pace | |
| Cohort 2 2025-09-25 | 0 | 0 | 1 | 0 of 2 | 15% | Definitions differ | |
| Cohort 2 2025-09-25 | 0 | 0 | 0 | 0 of 1 | 0% | Behind pace | |
| Cohort 3 2026-06-16 | 0 | 0 | 0 | 0 of 0 | 0% | No pace test | |
| Cohort 2 2025-09-25 | 0 | 0 | 1 | 0 of 2 | 0% | Behind pace | |
| Cohort 2 2025-09-25 | 0 | 0 | 0 | 0 of 2 | 0% | Behind pace | |
| Cohort 2 2025-09-25 | 0 | 0 | 0 | 0 of 0 | 8% | Definitions differ | |
| Cohort 1 2025-01-28 | 0 | 0 | 0 | 0 of 3 | 0% | Definitions differ | |
| Cohort 2 2025-09-25 | 0 | 0 | 0 | 0 of 0 | 0% | Definitions differ | |
| Cohort 3 2026-06-16 | 0 | 0 | 0 | 0 of 0 | 0% | Definitions differ | |
| Cohort 2 2025-09-25 | 0 | 0 | 0 | 0 of 1 | 67% | Definitions differ | |
| Cohort 2 2025-09-25 | 0 | 0 | 0 | 0 of 0 | 18% | Definitions differ |
| Step | Typical (median) | Slow (75th percentile) | Dated deals |
|---|---|---|---|
| PPA to financial close | 14 months | 19 months | 8 |
| Financial close to commercial operation | 19 months | 27 months | 24 |
| Financial close to operation, solar | 17 months | 26 months | 19 |
| Project | Waiting for | Since | Beyond the slow benchmark |
|---|---|---|---|
| ACWA Power 2 GW Hurghada Wind Project · 2,000 MW | financial close | 2025-02-18 | 2 months |
| Egypt 500 MW Wind Project · 500 MW | financial close | 2025-02-02 | 2 months |
| ACWA Power 442 MW Solar Project · 442 MW | financial close | 2023-12-20 | 13 months |
| Volobe Hydroelectric Project · 120 MW | financial close | 2023-05-30 | 22 months |
| Sasol Secunda Wind Project · 110 MW | financial close | 2024-02-28 | 13 months |
| Corbetti Geothermal Project · 50 MW | financial close | 2020-04-01 | 60 months |
| Guinea 40 MW Solar Plant · 40 MW | financial close | 2021-05-27 | 44 months |
| Ethiopia National Smart Metering Deployment | financial close | 2025-04-05 | 0 months |
| Impala Refineries Renewable Energy Supply (Discovery Green) | financial close | 2025-01-28 | 0 months |
| KP Lime Bowden Mine Renewable Energy Supply (Discovery Green) | financial close | 2025-01-28 | 0 months |
| Scatec Solar + BESS Projects (1.1 GWh Storage) | financial close | 2022-06-06 | 32 months |
AEI-evidenced delivery in compact countries since each compact was presented; partner-reported connections are not counted. Lags use dated PPA, financial close and commercial operation records; a step needs at least 5 dated pairs. Access pace compares the World Bank access series with the compact target; no verdict where the compact baseline and the World Bank series differ by more than 5 points.