MARKET / ETHIOPIA
#8Continent rank
27Deals tracked
$4,602mCapital tracked
21,525 MWPipeline
5,304 MWOperational (tracked)
6,345 MWInstalled RE (2024, IRENA)
57%Electricity access (2024, World Bank)
$126.4bnGDP (2025, World Bank)
2.64%RE capital / GDP (12M)

Market primer

structure, counterparties and bankability context
Region / power poolEastern Africa · EAPP
Main offtakerEthiopian Electric Power
RegulatorPetroleum and Energy Authority
PPA frameworkNot yet researched
Currency / convertibilityETB · Not yet researched
GDP per capita$933 (2025, World Bank)
Sovereign ratingsMoody’s · S&P · IMF DSA
Last updatedpending

Installed renewables

20152024, MW (IRENA)

Deals

every row source-linked
DateDealType$mConf
2026-07-17Aysha 1 Wind Projectproject_finance110B
2026-07-16Aysha 1 Wind Projectdfi_commitment110A
2026-07-15Aysha Wind Projectproject_finance110A
2026-06-30Ethiopia-Italy Financing Agreementcorporate_debt86A
2026-06-18Corbetti Geothermalequity_raise27
2026-05-15Ethiopia Rift Valley Geothermal Projectcorporate_debt59B
2026-05-13Ethiopia-France national grid modernisation dealcorporate_debt64B
2026-04-09IPT PowerTechcorporate_debt45B
2026-03-31P-REC Aggregation Facilitygrant11A
2026-03-30P-REC Aggregation Facilityguarantee_facility11A
2026-03-30Sun King Ethiopia Expansiongrantpledge150A
2026-03-28Ethiopian Renewable Energy Investment Prospectusproject_financepledge3,000A
2026-03-27Invest in Ethiopia 2026 Forum Agreementsproject_financepledge13,000A
2026-03-24Renewable energy and digital infrastructure programmeproject_finance86A
2026-02-28Gridworksequity_raise400B
2026-02-10Building Resilience for Food and Livelihoods Ethiopia Component Programgrantpledge26A
2026-02-10Building Resilience for Food and Livelihoods Ethiopia Component Programcorporate_debtpledge46A
2026-02-04Ethiopia Transmission Grid Expansion Programproject_finance400A
2026-02-04project_financepledge400C
2025-11-19Rusal Ethiopia Aluminium Smelterequity_raise1,000
2025-11-06Aysha II Wind Farmproject_finance257A
2025-09-11Renewable Integrated Sustainable Energy and Digitalisation (RISED) Programmeproject_finance140B
2025-08-11ASCENT Ethiopia Programgrant424B
2025-05-29Hainan Drinda New Energy Technologycorporate_debt360B
2025-05-29CSI Solarcorporate_debt250B
2025-04-24Ethiopian Electric Utility (EEU) \corporate_debt30B
2025-01-12Aysha 1 Wind Power Projectproject_finance620A

Project pipeline

ProjectTechMWStatus
Karadobi, Mabil, and Mendaya Hydropower DamsHydro10,000early_development
Mingyang Ethiopia Renewable Energy ProjectHybrid8,400late_development
Grand Ethiopian Renaissance Dam (GERD)Hydro5,150operational
Koysha Hydropower DamHydro1,800construction
3 major solar projects + 100 kWp Warsa Village solarSolar400early_development
Aysha 1 Wind ProjectWind300financing
Ethiopia Rift Valley Geothermal ProjectGeothermal150early_development
Weranso Solar PV ParkSolar150late_development
Gad IISolar125late_development
Aysha II Wind FarmWind120operational
WeransoSolar100late_development
Corbetti GeothermalGeothermal50late_development
Corbetti Geothermal ProjectGeothermal50late_development
Phoenix Group Mining FacilityHydro30operational
Somali Region Solar Plants (4 sites)Solar2operational
Gashamo Solar Power ProjectSolar1operational
Dome Gero Solar Power ProjectSolar1operational
Dig Solar Power ProjectSolar0operational
NusDiriq Solar Power ProjectSolar0operational
Merqan Solar Power ProjectSolar0operational
Africa Mini Grids ProgramSolartendered
Ethiopia Solar Mini-Grid ProjectsSolartendered
Degehabur–Kebridehar and Hurso–Ayisha Transmission LinesGridearly_development
Ethiopia Transmission Grid Expansion ProgramGridearly_development
Rusal Ethiopia Aluminium SmelterHydroearly_development
Ethiopia Bioethanol and SAF Production InitiativeOtherearly_development
Ethiopia 1,000-site Minigrid ProgrammeSolarearly_development

Tariffs & policy

DateProgram / dealUS¢/kWhConf
2025-10-29Cryptocurrency Mining Tariff Reform (Baseline)4.00B
2025-10-29Cryptocurrency Mining Tariff Reform (Peak Hours)6.00B
2026-07-17US AD/CVD Circumvention Investigation on Ethiopian Solar Cells
US Department of Commerce
2026-07-01National Electrification Programme (NEP) Phase III
Ministry of Water and Energy (Ethiopia)
2026-07-01National Electrification Programme (NEP) Phase III
Ministry of Water and Energy (Ethiopia)
2026-06-01Local contractor participation plan
Ministry of Urban and Infrastructure
2026-05-26National Energy Policy 2026
Ministry of Water and Energy; Council of Ministers
2026-05-25National E-Mobility Strategy and Implementation Framework
Government of Ethiopia
2026-03-23Directive 1064/2025 Amendment
Ministry of Finance
2026-03-23Investment Incentive Directive
EIC
2026-03-23National Energy Compact
Ministry of Water and Energy
2026-03-11National Energy Compact
Government of Ethiopia; World Bank
2026-02-17Investment Incentive Framework Operational Directive
Government of Ethiopia
2026-02-15National Nuclear Programme Infrastructure Development
Ethiopian Nuclear Energy Commission (ENEC)
2025-10-29National Energy Compact – Ethiopia (2024–2030)
MoWE; EEP; EEU; MoF; PEA; EIH; CDMU; NECSC
2025-10-29Draft Investment Incentive Regulation
Ministry of Finance, Government of Ethiopia
2025-10-29Cryptocurrency Mining Tariff Reform
Ethiopian Electric Power (EEP)
2025-10-15Green Skills and Renewable Energy TVET Integration Strategy
Ministry of Labour and Skills
2025-09-24Tariff revision for off-grid solar power & partnership with International Solar Alliance
Ministry of Water & Energy; Ethiopian Electric Utility; International Solar Alliance (ISA)
2025-06-03Draft Water and Energy Policy
Ministry of Water and Energy (Ethiopia)

Recent coverage

from the archive
2026-07-17US will investigate solar cells from Ethiopia for potential tariff circumvention
The US tariff circumvention probe directly threatens Ethiopia's emerging solar manufacturing hub, specifically Toyo Solar's 4 GW plant, by potentially applying retroactive duties on its US exports.
2026-07-17Ethiopia’s largest wind power project advances following $110 million AfDB funding approval
AfDB's $110 million approval for the $508 million Aysha 1 project marks a critical step for Ethiopia's first utility-scale private wind IPP, establishing a template for future private energy investments under the country's revamped PPP framework.
2026-07-17ET: AfDB Approves US$110 Million for Ethiopia’s Largest Wind Power Project The African Development Bank (AfDB) Group has approved a financing package of up to US$110 million to support the development of Ethiopia’s first
Confirms AfDB's $110M approval for Ethiopia's Aysha 1 wind IPP, already logged with more detail (300MW capacity, project name) from prior coverage — no new data here.
2026-07-17The African Development Bank Group has approved up to 110 million US dollars for Ethiopia’s 300 MW Aysha Wind Project, the country’s first privately developed wind power plant. The project forms part of a 508 million US
Secondary repost of the AfDB approval already logged from AfDB's own press release; no new registry-grade data.
2026-07-17African Development Bank Approves $110 Million for Ethiopia’s Largest Wind Power Project
AfDB's board approval confirms the $110m concessional tranche (AfDB/CTF/SEFA) for Ethiopia's first wind IPP and reveals the full $508m capital stack, including $381.1m still to be mobilised from other DFIs before financial close.
2026-07-17News: AfDB approves $110 million for Ethiopia’s first private 300 MW wind power project
Confirms AfDB's $110m commitment to Ethiopia's first private wind IPP (Aysha 1, 300MW) — re-reports ground already logged from the prior day's coverage, no new terms.
2026-07-17AfDB Approves $110m for Ethiopia's First Independent Wind Power Project #EBR_News Jul 17, 2026 The African Development Bank Group (AfDB) has approved a financing package of up to US$110 million for the 300-megawatt Aysha
AfDB's $110m board approval (part of a $508m package) financial-closes the debt anchor for Ethiopia's first privately-developed wind IPP, a template AMEA Power and other DFIs can replicate for the country's next wave of IPP wind/solar.
2026-07-16Kenya to pay higher tariffs for Ethiopian electricity under renewed deal
Kenya Power's forced reliance on costlier Ethiopian imports — a direct consequence of its 2018 IPP moratorium — pushes its import tariff to ~15.5c/kWh a year ahead of schedule, signalling EEU's rising pricing leverage as Kenya's cheapest domestic-generation alternative stays blocked.
2026-07-16African Development Bank Group approves $110 million for Ethiopia’s first 300MW independent wind power project
disclosed size $110 million; capacity 300MW; builds on prior coverage — trace "independent" in Storyline for the history
2026-07-14Kenya vs South Africa: What the Ethiopian Power Deal Teaches Eskom About Grid Sharing
builds on prior coverage — trace "Sharing" in Storyline for the history
2026-07-14Kenya-Ethiopia Power Deal Connects 10,000 New Customers Amid Regional Grid Integration
builds on prior coverage — trace "Connects" in Storyline for the history
2026-07-14Last week, our partners at CLASP announced a significant milestone: 19 companies across Ethiopia, Kenya, and Nigeria will receive a combined USD 1.5 million to scale productive-use solar technologies—solutions that do mo
disclosed size USD 1.5 million; builds on prior coverage — trace "CLASP" in Storyline for the history
2026-07-13A rewarding day of knowledge sharing and industry collaboration in Ethiopia! We upskilled local solar technicians via interactive technical sessions and on-site simulations. The training focused on solar system installat
builds on prior coverage — trace "knowledge" in Storyline for the history
2026-07-10Ethiopia attracted a record $4.32 billion in Foreign Direct Investment (FDI), up 8% from the previous fiscal year, as sweeping economic reforms and renewable energy investments boosted investor confidence, according to t
Ethiopia's record FDI inflow highlights the impact of recent macroeconomic reforms on investor sentiment, though the renewable energy component remains an aggregate figure rather than a specific project transaction.
2026-07-08Ethiopia: EPC contracts signed for transmission works
builds on prior coverage — trace "contracts" in Storyline for the history