None
- Debt capacity
- Tariff for 12% equity
- 6-month payment delay
- Lender terms
Bazma Solar is a 350 MW solar pv;bess project in Tunisia. The tracked project status is early development.
| Project | Bazma Solar · PRJ-0309 |
| Market | |
| Region | Northern Africa |
| Power pool | COMELEC |
| Technology | solar pv;bess |
| Capacity | 350 MWsource ↗ · Source linked |
| Status | early development |
How much debt this project carries, the tariff it needs for a 12% equity return, and whether it survives a six-month offtaker payment delay, under each structure.
About 621 to 675 GWh a year at a 22% capacity factor (AEI technology benchmark).
Enough electricity for about 308,000 to 335,000 people at Tunisia's average use of 2,016 kWh a person (2025).
About 378,000 tonnes of CO2 a year avoided if it displaces average grid generation (560 g/kWh, 2025).
Grid power also serves business and industry, so the people figure is a comparison, not a count of connections. Sources: AEI capacity-factor benchmarks, Ember electricity data (CC-BY-4.0), World Bank population.
The public record identifies Bazma Solar. Individual access gives you the research needed to assess its commercial position, subject to what has actually been disclosed.
Paid access adds the evidence layer; field status and package availability remain visible on each record.
Open the project’s recorded commercial terms, sources, missing evidence and comparable context in the subscriber workspace.