apply realization-rate assumptions to the announced/construction pipeline
Realization rates below are analyst assumptions you can edit — not reported data. Already-operational capacity (30,990 MW) is excluded from the projection.
Stage
Reported MW
Reported
Realization %
Projected MW
early development
172,526
34,505
late development
72,931
25,526
tendered
5,640
2,820
ppa signed
21,475
13,959
financing
5,782
4,625
construction
36,670
34,836
stalled
330
33
cancelled
0
0
315,353 MW in the non-operational pipeline · projected additions at these rates: 116,305 MW (derived, not reported)