None
- Debt capacity
- Tariff for 12% equity
- 6-month payment delay
- Lender terms
Eritrea 12 MW Mini Grid Project - Teseney is a 6 MW Solar project in Eritrea. The tracked project status is late development.
| Project | Eritrea 12 MW Mini Grid Project - Teseney · PRJ-0389 |
| Market | |
| Region | Eastern Africa |
| Technology | Solar |
| Capacity | 6 MWsource ↗ · Source linked |
| Status | late development |
How much debt this project carries, the tariff it needs for a 12% equity return, and whether it survives a six-month offtaker payment delay, under each structure.
About 11 to 12 GWh a year at a 22% capacity factor (AEI technology benchmark).
Enough electricity for about 84,000 to 91,000 people at Eritrea's average use of 127 kWh a person (2024).
About 6,700 tonnes of CO2 a year avoided if it displaces average grid generation (578 g/kWh, 2024).
Grid power also serves business and industry, so the people figure is a comparison, not a count of connections. Sources: AEI capacity-factor benchmarks, Ember electricity data (CC-BY-4.0), World Bank population.
The public record identifies Eritrea 12 MW Mini Grid Project - Teseney. Individual access gives you the research needed to assess its commercial position, subject to what has actually been disclosed.
Paid access adds the evidence layer; field status and package availability remain visible on each record.
Open the project’s recorded commercial terms, sources, missing evidence and comparable context in the subscriber workspace.